A tendering process will need to be completed to decide which provider is awarded a contract in each patch. The tender process was opened on 8 April 2022.
This is detailed timetable:
8
|
Step
|
Date
|
1
|
Opening the tendering process
|
8 April 2022
|
2
|
Submit tenders
|
May 2022
|
3
|
Provider interviews
|
End of May 2022
|
4
|
Letters, feedback and standstill period
|
June 2022
|
5
|
Award new contracts
|
July 2022
|
6
|
Transfer period for providers
|
July onwards - for at least 6 months
|
7
|
Embedd the new operating model
|
August onwards
|
People who receive the home care service and their families, when appropriate, will receive regular information about our plans. If the tender process involves any changes to the nature of their care, we will share information and discuss with them in good time.
Anyone affected by these changes will receive the full support of their local health and social care team.
All care and support staff are valued, and their jobs are crucial and safe. People who receiving home care today will continue to receive support for as long as they need it.